Foundation and Drainage. If the generator
set is attached to a shipping platform, this will provide an
adequate foundation. Otherwise, use planks, timbers,
logs, ammuntion boxes, or other available material to
prevent the skids from sinking into soft earth or sand. In
no case should the foundation exceed a height of six
inches and should
be level. Provide drain holes at ground level of the
revetment walls to insure the water is drained aw, from
the generator set. Drainage trenches a sumps must be
provided where the terrain is no, suited to adequate
drainage.
(4)
Wall Construction. Arrange sand bags
according to the dimensions shown in figures 4-8 thru 4-
10. Place sand bags so they overlap each other as
shown in figures 4-11, 4-12, and 4-13.